 The Plan On The Net .com User Guide  
| |
| Project Reporting And Analysis | |
|
Plan On The Net .com provides a wide range of reports and data analysis.
The following reports and analysis are available:
You can select the reports and analysis that you wish to view by toggling the appropriate report selector: | |
![]() | |
|
Select the level of report detail by opening the appropriate sections of the project plan: | |
![]() | |
| Tasks By Resource | |
| To view the tasks and assignments for each resource, toggle the Tasks-By-Resource report. Open up the resource folder of the project plan to the level of detail that you need. Tasks and assignments will be listed under each resource. To open up all resources in one click, select the Easy Open link Resources. | |
![]() | |
| Resources By Task | |
| By default, whenever you open up the Task section of a project plan, each task will have resource assignments listed. To open up all tasks in one click, select the Easy Open link Tasks. | |
| Critical Path Tasks | |
| By default, whenever you open up the Task section of a project plan, each task that is on the critical path will be marked with "CP" (critical path). To open up all tasks in one click, select the Easy Open link Tasks. | |
| Planned | |
| To view the original data that was entered as part of your planning, toggle the Planned report. | |
| Scheduled | |
To view the scheduled data calculated by Plan On The Net .com, toggle the
Scheduled
report.
For tasks, assignments and resources, this report shows:
Costs for tasks, assignments or resources.
Start dates
Finish dates
Effort
| |
| CPM DRAG Analysis | |
|
This report provides DRAG analysis to assist the project manager in
the most effective use of money and resources for best return on investment
(ROI).
Late Start: The latest a task can start without affecting the project. Late Finish: The latest a task can complete without affecting the project. Total Float: Also known as Total Slack: how much a task can slip without delaying the end of the project. DRAG: (Devaux's Removed Activity Gauge) The amount of time a project is adding to the total length of the project. Only tasks on the Critical Path will have a non-zero DRAG. A task that reduces it's DRAG to zero will come off the critical path, moving another task onto the critical path. For more information on the CPM DRAG metrics please see the non-affiliated site Total Project Control . | |
| Percentage By Effort And Cost | |
| This report shows how every resource, task and assignment, contributes on a percentage basis to the total project cost and effort. | |
| Quick Tracking | |
Quick Tracking shows the latest data on project actuals:
Actual start
Actual percentage complete
Actual effort expended
Actual cost
| |
| Earned Value Details | |
This report shows the detailed actuals data that has been captured in
support of Earned Value Management.
For each assignment, the report shows:
The date that a report was made.
The actual percentage completion at the reporting date.
The actual effort expended at the reporting date.
| |
| Projected Costs And Completion Dates | |
| Based upon the actuals captured for projected tracking, Plan On The Net .com will estimate a projected (based upon linear projection) completion date and cost for individual tasks and the project has a whole. | |