|
|
| Features | |
|
Plan On The Net .com allows corporations to
create project plans at a central web site,
track project completion using earned value management (EVM),
track project issues and allows the sharing and collaborative maintenance of
project data by multiple users and corporate partners.
In addition, comprehensive data is provided for resource analysis; data is readily exportable to MS Excel for further analysis. Plan On The Net .com gives your team access to project data anytime, from anyplace. | |
| Email Enabled Project Plans | |
Automatically send email to resources as tasks are about to start or are
becoming due to complete.
| |
| Earned Value Management | |
Maintain tracking data for each project assignment.
We keep tracking history for trend data analysis.
Display Earned Value histograms for Cost and Time. We provide both!
Export Earned Value data to Excel for further analysis!
We make Earned Value simple! We make you effective!
For more information on Earned Value Project Management, please see
non-affiliated site: | |
| Global And Private Resources | |
Share global resources across multiple projects!
Define resources private to a specific project.
Use resources from the global resource project in any of your
individual projects.
Get a total program office view of all your projects.
In one view get an analysis of how much is being spent on global resources,
local resources.
Review how much each individual project is contributing to global resource
costs.
See an overview of how global resources are being allocated (overburdened?)
across time.
Individual projects can mix local resources and global resources.
| |
| Project Encryption | |
Project data is encrypted when you use your project encryption password.
Your project is stored encrypted - we do not store your project encryption
password.
If project encryption password is lost,
we will not be able to recover your project data.
| |
| Critical Path, CPM DRAG | |
Critical path tasks are automatically identified.
The Analysis page shows CPM DRAG as described in Total Project Control and the book "Total Project Control" by Stephen A. Devaux (Wiley) 1999 ISBN 0-471-32859-6. For tasks not on a critical path, the analysis page shows how much a task can slip (total float or slack) and the latest start and finish times for a task, without the task affecting the planned completion date of a project. | |
| Collaboration | |
|
Collaboration is possible because the entire project team has instant
access to the latest project schedule from anywhere on the net.
Collaboration is easily extended to your corporate partners that also need
access to current project plans.
| |
| Resources | |
Resources can be setup on a per-project basis.
Resources are setup in a hierarchy such as organization, department and
person.
Each resource and department can have an associated dollar cost.
Each resource can have an associated quantity (i.e. "20 engineers").
Attach vacation or "not available" periods on a per-resource basis.
The scheduler will schedule assignments around these unavailable periods!
| |
| Tasks | |
Organize your project into a hierarchy of tasks and task folders.
Associate dependencies to tasks or task folders.
Assign resources to tasks from the resource (private or global).
Assign a specific resource or anonymously by assigning a department.
Track with actual start dates, percentage completion and effort expended.
| |
| Project Costing | |
A very important part of the software is the ability to provide a variety
of project costing data.
Cost data is always current with the latest project data.
Costing is provided for every resource and resource level.
Costing is provided for every task, task folder and assignment.
Costing is provided for actual work done and projected work.
You have the ability to restrict which users can see financial data.
| |
| Project Analysis | |
Analysis shows the percentage cost and effort contribution at every level.
Tracking data can be compared against planned data.
Based upon tracking data, system will estimate projected completion
dates and costs.
You have the ability to restrict which users can see financial data.
| |
| Project Plan Export | |
Export project and analysis data to your computer in CSV format.
Export earned value management data.
Import data into a program such as Microsoft Excel for further analysis.
| |
| Graphical Views | |
Two types of Gantt charts: simple and fully interactive.
Resource utilization is also shown on a Gantt charts.
Display for all resources and resource departments.
Vacation days are clearly visible.
Print charts to your printer.
Graphics shows planned, actual and projected data in a single view.
Histogram view of earned management data. Shows EVM trend data.
| |
| Track Project Issues | |
Track status changes and issue amendments.
Add new issues.
Categorize issues according to your own category list.
Issue list can viewed in a tree structure. You choose the tree order.
Issues can be amended with time-stamped change notes.
Issue creation can be restricted to a subset of your project team.
Issue contents can be encrypted.
| |
| Program Office Administration | |
The program office administrator can:
Add, modify and delete users.
Setup vacation days common to all projects.
Create and maintain global groups for ease of access control to projects.
Re-assign project ownership.
| |
| Individual Administration | |
Non-admin users can:
Create projects.
Provide access to groups and other users.
Create and maintain private groups for ease of access control to projects.
Setup vacation days specific to projects.
| |
| Access rights | |
Can be set for each user or group, per project.
Update access allows tasks and resources to be added and modified.
Update access allows individual resource costs to be viewed and modified.
Cost access allows project costs to be viewed.
Version control allows a user to version a project plan.
| |
| Version control | |
Easy to use.
Allows project plan snapshots to be taken.
Earlier versions can be reviewed instantly by members of your project team.
Ability to revert back to prior versions.
| |
| Project Reporting And Analysis | |
|
Plan On The Net .com provides a wide range of reports and data analysis.
The following reports and analysis are available:
You can select the reports and analysis that you wish to view by toggling the appropriate report selector: | |
![]() | |
|
Select the level of report detail by opening the appropriate sections of the project plan: | |
![]() | |
| Tasks By Resource | |
| To view the tasks and assignments for each resource, toggle the Tasks-By-Resource report. Open up the resource folder of the project plan to the level of detail that you need. Tasks and assignments will be listed under each resource. To open up all resources in one click, select the Easy Open link Resources. | |
![]() | |
| Resources By Task | |
| By default, whenever you open up the Task section of a project plan, each task will have resource assignments listed. To open up all tasks in one click, select the Easy Open link Tasks. | |
| Critical Path Tasks | |
| By default, whenever you open up the Task section of a project plan, each task that is on the critical path will be marked with "CP" (critical path). To open up all tasks in one click, select the Easy Open link Tasks. | |
| Planned | |
| To view the original data that was entered as part of your planning, toggle the Planned report. | |
| Scheduled | |
To view the scheduled data calculated by Plan On The Net .com, toggle the
Scheduled
report.
For tasks, assignments and resources, this report shows:
Costs for tasks, assignments or resources.
Start dates
Finish dates
Effort
| |
| CPM DRAG Analysis | |
|
This report provides DRAG analysis to assist the project manager in
the most effective use of money and resources for best return on investment
(ROI).
Late Start: The latest a task can start without affecting the project. Late Finish: The latest a task can complete without affecting the project. Total Float: Also known as Total Slack: how much a task can slip without delaying the end of the project. DRAG: (Devaux's Removed Activity Gauge) The amount of time a project is adding to the total length of the project. Only tasks on the Critical Path will have a non-zero DRAG. A task that reduces it's DRAG to zero will come off the critical path, moving another task onto the critical path. For more information on the CPM DRAG metrics please see the non-affiliated site Total Project Control . | |
| Percentage By Effort And Cost | |
| This report shows how every resource, task and assignment, contributes on a percentage basis to the total project cost and effort. | |
| Quick Tracking | |
Quick Tracking shows the latest data on project actuals:
Actual start
Actual percentage complete
Actual effort expended
Actual cost
| |
| Earned Value Details | |
This report shows the detailed actuals data that has been captured in
support of Earned Value Management.
For each assignment, the report shows:
The date that a report was made.
The actual percentage completion at the reporting date.
The actual effort expended at the reporting date.
| |
| Projected Costs And Completion Dates | |
| Based upon the actuals captured for projected tracking, Plan On The Net .com will estimate a projected (based upon linear projection) completion date and cost for individual tasks and the project has a whole. | |
| Earned Value Management (EVM) | |
| About EVM | |
|
EVM was originally created for tracking and monitoring large and complex
projects.
EVM provides an effective
method of tracking a project and for measuring real project progress and
overruns (cost or effort).
EVM also provides the project manager a tool for measuring actual worked performed against the planned (budgeted) work schedule as well as indicating cost or effort overruns against budgeted cost or effort schedules. If you are not familiar with EVM, you can review some of the many excellent web sites on EVM. As a reference, we provide the following link (not affiliated with this site): Earned Value Management Web Site. | |
| We Make It Simple | |
|
This site makes EVM simple to use and provides you, the project
manager, an effective tool to use on your projects.
There are two main activities: (1) Entering tracking data and (2) Reviewing the analysis. | |
| Entering Tracking Data | |
|
Tracking data is entered for each task assignment.
You should enter how much real progress has been made (percentage complete),
the actual effort (time) expended, and the date of the entry.
That's it!
The most important aspect of this data entry, is to correctly assess the percentage completion of an assignment. You should not enter percentage completion based upon hours expended or money spent. Enter an assessment of how complete the assignment is. The software keeps track of previous entries and so an automatic trend dataset is maintained. To enter tracking data, go to the project worksheet and select the "pen" icon
next to the task assignment that you want to update:
program office | |
![]() | |
| Reviewing EVM Analysis | |
| You can review histograms directly on this site, or you can export EVM data to a spreadsheet on your computer for further detailed analysis and graphing. | |
| Review EVM Directly On This Site | |
To review both histograms, go to the EVM review page:
program office pick project plan earned value.
This page will present two histograms for earned value trend data:
EVM by cost and and by effort (time) are both presented.
The following image shows a sample histogram. | |
![]() | |
| Planned Cost Budget (BCWS) | |
| This data shows the planned project cost. BCWS: Budgeted Cost for Work Scheduled. This is your reference baseline for measuring project progress. | |
| Earned Value (BCWP) | |
|
This data shows the trend for
earned value.
This is how much real progress has made on the project relative to how much
progress should have been made.
This trend is independent of how much effort (or money) has been spent to date.
BCWP: Budgeted Cost for Work Performed.
The schedule variance indicates how much ahead (or behind) the project is, based upon the actual real progress made. | |
| Actual Cost (ACWP) | |
|
This data shows the trend data for
actual cost
to date. The plots show how much over (or under) spending is taking place,
relative to the planned cost schedule.
ACWP: Actual Cost for Work Performed.
The cost variance indicates how much over (or under) spending is currently taking place, relative to the planned spending schedule. | |
| Exporting Data To A Spreadsheet | |
|
You can export the EVM analysis data to your computer in the form
of a CSV (comma separated) file that can be used directly in your
spreadsheet program.
From the EVM analysis page (see navigation in section above), select the export current view link. You will be prompted to save the data in a file or opened with your spreadsheet program. Due to different PC configurations, we suggest that you first save the file and then open with your spreadsheet program. The following image shows some EVM data plotted on a graph using MS Excel. | |
![]() | |